A Change Control Board is

A formally constituted group of stakeholders responsible for announcing changes to the project baseline
A formally constituted group of stakeholders responsible for rejecting or approving changes to the project baseline
Functionally the same as a project sponsorship board
Any group of stakeholders that suggest changes to a project baseline